Rs 5,700 cr Project cost. Adani Energy Solutions Limited (AESL) announced financial closure on Monday
– Mumbai’s electricity demand is expected to touch 5,000 MW by 2024-25 from the current peak demand of 3,500-4,000 MW
– The island city has only 1,800 MW of embedded generation capacity and the existing transmission corridors face capacity constraint risks
– Due to new Metro lines and EV charging stations, demand to rise by at least 150 MW in a year.
The HVDC project will offer a technological upgrade to the city. This link is the need of the hour and will offer Mumbai a brighter and greener future. The project will help accelerate the city’s decarbonization and its net zero journey.
Anil Sardana | MD, Adani Energy Solutions Limited
– The existing transmission network is close to its full capacity in terms of utilisation
– In case of outage of any transmission line (due to fault or maintenance), the system shifts to operate in a critical state where any further tripping can result in a load shedding or a blackout situation as was witnessed in October 2020
बांग्लादेश की राष्ट्रीय क्रिकेट टीम के विकेटकीपर-बल्लेबाज लिटन दास ने शनिवार को पाकिस्तान की राष्ट्रीय…
शोटाइम: तमाशा में मंच बनाना एक रोजमर्रा का काम हैशोटाइम: तमाशा में मंच बनाना एक…
आखरी अपडेट:17 मई, 2026, 00:04 ISTरिपोर्टों से पता चलता है कि पार्टियाँ एक सौदा पूरा…
ग्रामीण महाराष्ट्र में न्यूरोलॉजिस्ट और उन्नत स्ट्रोक-देखभाल सुविधाओं की भारी कमी के बीच इस पहल…
ठाणे: महात्मा फुले चौक पुलिस ने पिछले कुछ हफ्तों में कल्याण में कई घरों में…
सूर्या और तृषा कृष्णन की नई फिल्म 'करुप्पु' 15 मई को सुपरस्टार में रिलीज हुई…